|
After analyzing this
data, tank dump and recharges were moved to every two weeks,
sometimes more frequent. It became evident that this situation
needed to be better controlled to help remove the contaminants
that are causing the cleaner to be used.
INVESTIGATION/TESTING
Testing through out
this process showed that there were several issues that could be
controlled in the cleaner stages of the system that would aide
in resolving the issues on the paint defects. The testing
showed that the cleaner’s Free Alkalinity level is quickly being
used up by strontium leeching out of the parts and tying up the
cleaner. As alluded to above, in order to keep the Free
Alkalinity levels at a sufficient level, overall concentrations
needed to be raised to a point in which the concentration would
cause surfactant residue problems.
Combined with this,
the cleaning of the cleaner tanks themselves was virtually
non-existent due to safety concerns. The piping and the tanks
were built up with residues that would also tie up the cleaner
and also produce floating residues that would help cause the
paint defect.
Due to the above, two
actions were taken. The chemical manager and the paint engineer
worked with safety to implement the proper safety equipment and
cleaning processes such that the tanks and piping within these
systems were properly maintained. The second issue that the
chemical manager worked on was to investigate and research ultra
filtration units in which the ultra filter would remove the
portions of the cleaner that are “used-up”.
Research into the
different units on the market led to the purchase of two units
from Arbortech out of Illinois. One unit was purchased for each
cleaner tank on the system and implemented in the February-March
timeframe of 2006. Each unit is positioned in front of each of
the tanks and dedicated to each tank.
Once these units
were implemented, the chemical manager continued to perform the
daily Total and Free Alkalinity Testing on each of the tanks.
The dumping frequency was removed and tank dumps were moved to
dumps based off of data from the data collected from the cleaner
testing.
The chemical manager also took the task of taking
daily throughput readings to ensure that the membranes are
operating efficient.
RESULTS
Since the implementation of the ultra filtration
unit from Arbortech we’ve been able to move the cleaner tank
dump and recharges from a two week frequency to an average of
5.5 weeks over the course of the first year of operation. This
frequency increase has provided the manufacturer with cost
savings on cleaner as well as on waste treatment costs, not to
mention water savings.
Cost/Benefit
Costs
Ultra-filter Units $19,756
each $39,512
Stands
for Units $1,040
each $2,080
Miscellaneous (Fittings, labor) $4,000
Total $45,592
Benefits (Actual)
Cleaner
Costs
$37,901.74
Waste
Treatment
Costs $ 7,108.92
Total $45,010.66
ROI
ROI=Costs
of Implementation/Benefits
ROI=45,592/45,010.66
ROI=1.01 years
The overall cost savings through the course of the first year is
$45,010.66 not including improved cleanliness of the parts
coming out of the wash operation within the system and the
downstream effect. With the implementation costs of $45,592,
the Return on Investment is in effect 1 year. |